Situation Report · October 12, 2026
A magnitude 7.7 earthquake struck central Panama on October 9, 2026. Miyamoto has dispatched an expert team to Panama, and our engineers have summarized the shaking, the exposure, and the priorities for response and recovery.
On October 9, 2026, a magnitude 7.7 earthquake struck central Panama, with its epicenter approximately 12 km west-southwest of Pitaloza Arriba, Herrera Province, at a depth of 12.6 km. The event was followed by a significant aftershock sequence, including a reported magnitude 6.6 event. This preliminary engineering and recovery assessment summarizes the available information and the engineering priorities for response and recovery.
Miyamoto International has dispatched an expert team to Panama. We will update this assessment as field observations become available.
7.7
Moment magnitude
12.6 km
Focal depth
1.36M
People at MMI VI or above
Findings
- USGS PAGER has revised its alert for shaking-related fatalities to Yellow, indicating that some casualties are possible. PAGER continues to estimate significant economic losses, at 1 to 20 percent of Panama’s GDP.
- Strong shaking was experienced across Herrera, Los Santos, Coclé, Veraguas, and Panama Province. Authorities report damage to more than 400 homes, 419 schools, 21 health facilities, and 9 bridges, as well as historical structures, roads, and water treatment plants.
Shaking intensity
The strongest shaking, MMI IX (violent), is concentrated around the epicenter in Herrera and Los Santos. Within Panama, an estimated 1,356,834 people and 440,337 buildings were exposed to MMI VI or above.

Most affected corregimientos
Of the 567 corregimientos within the ShakeMap, 412 experienced MMI VI or higher. The 15 most affected all reached MMI IX, led by Ponuga (Santiago), Llano de Catival (Mariato), and Tonosí (Tonosí).

Cities exposed
USGS PAGER lists nine cities in the strongest shaking, with a combined population of 172,313. Tonosí experienced MMI IX. Llano de Piedra, Macaracas, Las Tablas, and Pocrí experienced MMI VIII.

The maps show population and building exposure only. They are not damage, casualty, or loss estimates.
Anticipated structural performance
The shallow focal depth and strong ground shaking present significant concerns for vulnerable structures, particularly older masonry buildings, nonductile reinforced concrete construction, and informal housing.
Unreinforced masonry
Out-of-plane wall failures, diagonal cracking, parapet instability, partial collapse
High
Older reinforced concrete
Column shear damage, joint distress, inadequate confinement, residual drift
Moderate to high
Modern reinforced concrete
Nonstructural damage, partition failures, localized structural distress
Moderate
Informal housing
Inadequate connections, unstable walls, foundation deficiencies
High to very high
A substantial portion of damaged buildings may be repairable. However, repairability cannot be reliably quantified until systematic field assessments establish the extent of structural damage. Buildings with severe structural deficiencies, permanent deformation, or unstable load-bearing elements may require demolition.
Engineering response and recovery priorities
0 to 72 hours
Emergency Safety Assessments
Conduct rapid building safety evaluations, prioritize hospitals and emergency facilities, inspect critical bridges and infrastructure, identify unsafe structures, and support emergency shelter operations.
2 weeks
Detailed Engineering Assessments
Establish building-by-building damage classifications, evaluate repairability, identify demolition requirements, develop GIS-based damage inventories, and prioritize infrastructure restoration.
3 months
Recovery and Reconstruction Planning
Develop housing repair and reconstruction programs, prioritize school and healthcare rehabilitation, establish debris management systems, and implement community-based recovery strategies.
Early engineering assessment and intervention are essential to reduce temporary sheltering needs and impacts on communities. Engineering assessments and technical guidance expedite return-to-home models by supporting engineering-driven decision making and policy decisions.
The priority should be to move quickly from emergency assessment to actionable recovery decisions, allowing displaced families to return safely wherever possible.
Panama Earthquake Situation Report
Preliminary recovery outlook
Despite the earthquake’s magnitude and strong ground shaking, initial reports suggest that Panama has avoided the widespread structural collapse and catastrophic loss of life associated with some previous major earthquakes. Nevertheless, damage to vulnerable buildings and essential infrastructure may create substantial localized recovery needs, particularly in communities closer to the epicentral region.
The central engineering challenge will be to establish a reliable classification of affected structures into three categories:
- Safe for occupancy: buildings requiring no significant structural intervention.
- Repairable: buildings requiring engineering evaluation, stabilization, or structural and nonstructural repairs.
- Unsafe or beyond practical repair: buildings requiring restricted access, stabilization, or controlled demolition.
Rapid and consistent engineering assessments will provide the technical foundation for recovery planning, resource allocation, and reconstruction investment.
This report is preliminary and is based on information available at the time of writing, including initial public reports. It does not express or imply any warranty regarding the condition of specific structures, and its observations will be updated as field assessments progress.