Masterton Courthouse

Masterton Courthouse

In November 2011, the 101-year old Masterton Courthouse was closed — deemed unsafe to the public due to the risk of collapse in the event of an earthquake. The 900m2 building required strengthening to 100% NBS and re-roofing. General reconfiguration and refurbishment also was needed to bring the building up to modern standards and allow it to reopen for public use. A structural design had been proposed.

In January 2012, the Ministry of Justice began working with Miyamoto International NZ (formerly Miyamoto Impact) to project manage the building’s earthquake strengthening and refurbishment. When appointed, we recognized that the structural design being proposed was a very costly option – almost on par with demolishing the existing building and constructing a new courthouse. A peer review was recommended to assess if the proposed design represented the best solution for the Ministry. This review resulted in a new design that would half the cost and complete the work in a shorter time frame.

The Ministry approved the budget for the project and we proceeded with appointing the full design team. A part of our role was to collate the requirements from the different Ministry stakeholders into a brief that clearly articulated all their requirements. This brief meant the designers were fully informed from the outset. In addition, a clear scope of services and appointments for all consultants was provided, avoiding the need for additional fees. Seismic technologies deployed to upgrade the building included a seismic retrofit. This used fibre reinforced polymer (FRP) for both in plane and out of plane unreinforced masonry. Performance-based methods (alternate analysis methods) were used to justify existing unreinforced wall out of plane capacity. This eliminated costly wall strengthening.

Learnings from New Zealand and Miyamoto International’s Los Angeles and Milan offices were used in the project’s analysis and retrofit to deliver added value to the Ministry. Throughout the project, we provided clear leadership. This saw the right design team being appointed, costs controlled and a tender process that got the best outcome for the Ministry. By suggesting a peer review, Miyamoto International NZ’s initiative allowed the Ministry to save 50% on the previous design and saw the Courthouse reopen in early June 2013, ahead of the original timeframe.

Team Members

No data was found

Client

Ministry of Justice
NZ Government

Year

2013

Scale

-

Location

Masterton, Wairarapa

Masterton Courthouse

In November 2011, the 101-year old Masterton Courthouse was closed — deemed unsafe to the public due to the risk of collapse in the event of an earthquake. The 900m2 building required strengthening to 100% NBS and re-roofing. General reconfiguration and refurbishment also was needed to bring the building up to modern standards and allow it to reopen for public use. A structural design had been proposed.

In January 2012, the Ministry of Justice began working with Miyamoto International NZ (formerly Miyamoto Impact) to project manage the building’s earthquake strengthening and refurbishment. When appointed, we recognized that the structural design being proposed was a very costly option – almost on par with demolishing the existing building and constructing a new courthouse. A peer review was recommended to assess if the proposed design represented the best solution for the Ministry. This review resulted in a new design that would half the cost and complete the work in a shorter time frame.

The Ministry approved the budget for the project and we proceeded with appointing the full design team. A part of our role was to collate the requirements from the different Ministry stakeholders into a brief that clearly articulated all their requirements. This brief meant the designers were fully informed from the outset. In addition, a clear scope of services and appointments for all consultants was provided, avoiding the need for additional fees. Seismic technologies deployed to upgrade the building included a seismic retrofit. This used fibre reinforced polymer (FRP) for both in plane and out of plane unreinforced masonry. Performance-based methods (alternate analysis methods) were used to justify existing unreinforced wall out of plane capacity. This eliminated costly wall strengthening.

Learnings from New Zealand and Miyamoto International’s Los Angeles and Milan offices were used in the project’s analysis and retrofit to deliver added value to the Ministry. Throughout the project, we provided clear leadership. This saw the right design team being appointed, costs controlled and a tender process that got the best outcome for the Ministry. By suggesting a peer review, Miyamoto International NZ’s initiative allowed the Ministry to save 50% on the previous design and saw the Courthouse reopen in early June 2013, ahead of the original timeframe.

Client

Ministry of Justice
NZ Government

Year

2013

Scale

-

Location

Masterton, Wairarapa

More Projects

Tilt-Up, Warehouse & Distribution

West Corona Industrial Center

Corona, CA

Miyamoto International’s effort on the West Corona Industrial Center was 100 percent during the design [..]

View Project

Commercial, Entertainment, Retail

John Reed DTLA

Los Angeles, CA

John Reed Fitness is a revolutionary fitness chain owned by the RSG Group. What makes [..]

View Project

Commercial, High-Rise, Mixed-use, Residential, Retail

Reno Mixed-Use High Rise

Reno, NV

Miyamoto is engineering a 23-story, mixed-use, high-rise with three levels of underground parking, ground-level retail [..]

View Project

Lab and Science

University of California, Irvine, Medical Center Replacement Hospital, Phases 1 and 2

Torrance, CA

Miyamoto provided structural peer review services for the bridging and construction documents of this design-build [..]

View Project

Industrial, Tilt-Up

Tesla Flower Mound

Flower Mound, Texas

Tesla Flower Mound is a one-story tilt-up building that will house a Tesla SSD Center, [..]

View Project

Residential

Capitol Yards Apartments

West Sacramento, CA

Located just across the river from historic Old Sacramento, the West Capitol Commons housing complex [..]

View Project

Save lives, impact economies.

what we’re up to

Latest News & Updates

Subscribe to learn about new the latest in engineering news, solutions, and updates.

We care about your data in our privacy policy.